Call for Observing Proposals for the Plateau de Bure Interferometer

Observing proposals are invited for the IRAM Plateau de Bure Interferometer (PdBI), for the period May 15, 1997 to Nov. 15, 1997. The deadline for applications is March 6th, 1997. The available frequency range will be 82 GHz to 116 GHz for the 3mm band, and 210-245 GHz for the 1.3 mm band.

Details of the PdBI and the observing procedures are given in the document ``An Introduction to the IRAM Plateau de Bure Interferometer'' . Proposers should read this document carefully before submitting any proposal.

Proposals should be sent to

IRAM Scientific Secretariat
Interferometer Observing Proposal
300 Rue de la Piscine
F-38406 Saint Martin d'Hères Cedex
FRANCE

IRAM expects to schedule and complete between 20 to 30 projects in this period, with an elapsed time of at least two months between start and end of any given project. Selection will be based on scientific merit, technical feasibility, and adequacy to the instrument.

For this call for proposal, please note the following:

Proposal Category
Proposal should be submitted in one of the 4 strict categories defined below:
Category 1:
Proposals that ask for 3mm data ONLY. 1.3 mm receivers can still be used to provide either phase stability information or purely qualitative information such as the mere existence of fringes. The maximum available baseline length will be about 300 m.
Category 2:
Proposals that ask for 1.3mm data ONLY. 3mm receivers will be used for pointing and calibration purposes, but cannot provide any imaging. The maximum available baseline length will be about 200 m.
Category 3:
Proposals that ask for dual-frequency observations. The maximum available baseline length will be about 200 m.
Category 4:
Exploratory proposals: Proposals whose scientific interest justifies the attempt to use the PdB array beyond its guaranteed capabilities. This category includes for example long baselines observations, non standard frequencies for which tuning cannot be guaranteed, and more generally all non standard observations. These proposals will be carried on a ``best effort'' basis.

The proposal category will have to be specified on the proposal cover sheet, and should be carefully considered by proposers.

Maintenance

Heavy maintenance is foreseen for antennas 1 to 4. Accordingly, the Plateau de Bure array will operate:
- in 4 antenna configuration for May to August.
- in 5 antenna configuration for September, October and November.

Configurations
The configurations are given in Table 1.

   

4 Antenna configurations
Name Stations
D1 W05 W00 E03 N05
D2 W10 W01 E03 N09
C1 W20 W05 N09 N17
C2 E10 W09 N03 N15
B1 E16 E24 N11 N17
B2 W12 W09 E24 N20
A1 W27 W20 E23 N29
A2 W23 E04 E24 N29
Table 1: Plateau de Bure Interferometer: available configuration sets

5 Antenna configurations
Name Stations
D W05 W00 E03 N05 N09
C1 W05 W01 E10 N07 N13
C2 W12 W09 E10 N05 N15
B1 W12 E18 E23 N13 N20
B2 W23 W12 E12 N17 N29
A W27 W23 E16 E24 N29

With 5 antennas, the PdB interferometer offers 6 configuration sets:

Set 4 ant Config. 5 Ant Config. Main purpose
D D1, D2 D ``Low'' resolution at 1.3 mm
CD D1, C1, C2 D, C2 or C1 3.5'' resolution at 3mm, 1.8'' resolution at 1.3 mm
CC n.a. C1, C2 Slightly higher resolution than CD.
BC C1, C2, B1, B2 B1, C2 2'' resolution at 3 mm
BB n.a. B1, B2, C2 Better sensitivity than BC
AB B1, B2, A1, A2 A, B1, B2 1'' resolution at 3 mm

There is a possibility of choice between CD and CC arrays when configuration C2 has been performed for sources in which the resolution choice is unclear. At a higher resolution level, a similar choice between CC and BC or BB is possible.

1.3 mm band and dual-frequency observations
All antennas are now equipped with fully operational dual frequency receivers. The 3mm and 1.3mm receivers are aligned to within about 2'', allowing proper dual frequency observations.

Experience based on the past year shows that 1.3 mm observations are seldom feasible in summer time, and that such observations are possible only for objects transiting during the night of the August to October period. Accordingly, 1.3mm or dual-frequency projects for other objects will be considered as ``Category 4'' proposals, i.e. will be carried out on a best effort basis only, weather permitting.

Very long baselines: configuration A
Configuration A will NOT be scheduled for the next session.

Signal to Noise
The rms noise can be computed from

equation400

where

Receivers
Below 110 GHz, receivers offer best performances in LSB tuning with high rejection (20 dB): expected system temperatures are (in tex2html_wrap_inline604 scale) 150 to 200 K for the summer time. Above 110 GHz, best performances are obtained with USB tuning, low rejection (4 to 6 dB): expected system temperatures are 300 K at 115 GHz. DSB tuning is possible over the whole frequency range, but the system temperature may degrade significantly.

The 1.3 mm receivers give DSB tuning with typical T tex2html_wrap_inline606 below 50 K. Expected SSB system temperature are 400 to 500 K. However a relatively narrow resonance significantly degrades the performances near 245 GHz. The guaranteed tuning range is 210-245 GHz, but it may be possible to reach lower frequencies for specific cases. Higher frequencies are not feasible because of limitations in the triplers.

Coordinates and Velocities
The interferometer operates in the J2000.0 system. For best positioning accuracy, source coordinates must be in the J2000.0 system; position errors of up to 0.3'' may occur otherwise.

Please do not forget to specify LSR velocities for the sources. For pure continuum projects, the ``special'' velocity NULL (no Doppler tracking) can be used.

Coordinates and velocities in the proposal MUST BE CORRECT: A coordinate error is a potential cause for proposal rejection.

Correlator:
The correlator has 6 independent units, each being tunable anywhere in the 110-610 MHz band, and providing 4 choices of bandwidth/channel configuration: 160 MHz/64, 80 MHz/128, 40 MHz/256 and 20 MHz/256. For the 40, 80 and 160 MHz bandwidth, the two central channels may be perturbed by the Gibbs phenomenon (depending on continuum strength): it is recommended to avoid centering the most important part of the lines in the middle of the band of the correlator unit.

The 6 units can be independently placed either on IF1 (3 mm receiver) or on IF2 (1.3 mm receiver).

40 kHz resolution:
One (and ONLY ONE) of the 6 units has been retrofitted to offer a higher frequency resolution (40 kHz instead of 80 kHz). This is obtained by operating at half clock-speed and inserting an anti-aliasing filter of effective bandwidth 8 MHz. Because the filter reduces the input power to the sampler, this unit should be placed near the maximum amplitude of the IF bandpass: band edges must be avoided.

Sun Avoidance:
For safety reasons, the sun avoidance circle has been extended to 45 degrees. Please take this into account for your sources and for the calibrators.

Mosaics
The PdBI has mosaicing capabilities, but the pointing accuracy may be a limiting factor at the highest frequencies. Please contact S.Guilloteau in case of doubts.

Data reduction
Proposers should be aware of constraints for data reduction: Data reduction will be carried out on the dedicated HP workstations.

Local contact:
Depending upon the program complexity, IRAM may require an in-house collaborator instead of the normal local contact.

Technical pre-screening:
All proposals will be reviewed for technical feasibility in parallel to being sent to the members of the program committee. Please help in this task by submitting technically precise proposals. Scientific justification should be kept within 2 pages. Note that your proposal must be complete and exact: velocities, position and frequency setup must be exactly specified.

Non-standard observations:
Please contact S.Guilloteau in case of doubt about non-standard program feasibility.

The documentation for the IRAM Plateau de Bure interferometer includes documents of general interest to potential users:

More specialized documents are also available; they are intended for observers on the site (IRAM on-duty astronomers, operators, or observers with non-standard programs):

Finally, we would like to stress again the importance of the quality of the observing proposal. The IRAM interferometer is a powerful, but complex and unique instrument, and proposal preparation requires special care. Information is available in the documentation, and the IRAM staff can help in case of doubts if contacted well before the deadline. Note that the proposal should not only justify the scientific interest, but also demonstrate how the Plateau de Bure interferometer will bring new information.

Stéphane GUILLOTEAU


next up previous contents
Next: Scientific results Up: IRAM Newsletter 30 (January Previous: References

lucas@iram.fr